Thursday, August 23, 2007

CITY OF CHINO HILLS News

ANNUAL STREET MAINTENANCE PROJECT UNDERWAY

The City has awarded an $889,482 contract to American Asphalt South for the annual
street improvement project. The schedule is being adjusted to ensure that the Verizon
project to install fiber optics is completed before the slurry is applied on the affected streets.
Workers have been doing preliminary work including crack sealing, limited pavement repairs
(patching), and some pavement grinding. Hardy and Harper is the paving sub-contractor.
The streets listed below will undergo pavement grinding followed by curb-to-curb
construction of a one-inch layer of asphalt. Motorists will be diverted around the work areas.
Full closures are not anticipated.
Updated information will be posted on the City’s website, www.chinohills.org.
Schedules are subject to change due to a variety of factors including conditions in the field,
weather conditions, etc.